Willard Bay Facilities Improvement

Location of Work:

Willard Bay State Park, Utah

Completion Date:

October 30, 2002

Description:

This project was completed almost two months ahead of schedule. It included site improvements for multiple campgrounds and day-use areas.  Work included site utilities, concrete boat ramps, concrete walks, 8.5 acres of asphalt paving, precast flush restroom units w/ showers, pre-fabricated fish cleaning stations, pre-engineered metal group-use and picnic shelters, 5.5 acres of landscaping and irrigation.

Owner initiated changes included an additional Fish Cleaning Station, replacement of existing sanitary sewer line at South Marina, and cost difference to provide group and picnic shelters from preferred vendor.  Minor contract adjustment due to differences in unit price line items between bid quantities and actual quantities used.